Noordermeerdijk

SolarPark Noordermeerdijk

 
Realising a more than 100 MW solar park with a 33kV cable route of about 12km towards a substation TenneT (110kV).

Description

- Feasibility-study for the 330kV cable route and connection at a Wind Park (cable pooling).
- Engineering of the final cable route and connection at 110kV substation TenneT, in combination with the more than 100MW Solar Field Westermeerdijk (different client).
- Coordination of the permit process for cable route and substation.
- Preparation tender documents and supervising of tendering and realisation.